What are typical delivery lead times?
Lead time depends on whether a mock-up is required.
With mock-up:
- Approx. 17 weeks from order and final design approval
- 5 weeks: mock-up production and approval
- 12 weeks: serial production and delivery commencement
Without mock-up:
- Approx. 14 weeks from final design approval
Delivery sequencing is aligned with site programme and issued in advance to support tower-by-tower installation planning.