Yes, subject to structural and access validation.
Key assessments include:
- Existing floor load capacity
- Crane access or lifting feasibility
- Route width and manoeuvring clearance
- Integration with existing risers and service routes
Retrofit integration requires early-stage survey coordination to verify dimensional compatibility and installation sequencing.
Other FAQs
What site preparation is required?
The site preparation for pod installation requires a level and structurally verified floor slab, with marked neoprene support locations. Recessed installations must be coordinated early in the design phase. Neoprene pads help accommodate minor tolerances and ensure proper alignment with surrounding floor finishes.
How are pods moved safely on site?
Pods are safely moved on site using certified lifting systems, including lifting bushings and defined anchor points. Depending on weight and configuration, handling may involve cranes or forklifts. The lifting strategy is agreed in advance to ensure safe installation.
Are there dimensional or transport limitations?
Bathroom pods are typically delivered using standard UK trailers. One external dimension is generally kept under 2.45 m, while the second may extend up to 4 m. For larger configurations, split modular solutions or specialist transport arrangements are used. Transport planning is coordinated during the pre-construction stage to ensure alignment with site access strategy.