Pod weight depends on configuration and structural system.
Lightweight steel-frame pods:
- 400–600 kg/m² floor area load
- Typical total unit weight: 1–3 tonnes
Weight confirmation is issued during design coordination and is used to:
- Confirm slab load capacity
- Verify lifting method
- Plan craneage and logistics
- Assess high-rise installation sequencing
Load data is provided prior to manufacture to support structural verification.
Other FAQs
What are typical wall and base thicknesses?
The pod construction is finalized during the design coordination phase. Available base options include a standard concrete base (approximately 2400 kg/m³), a lightweight concrete base (approximately 1800 kg/m³), and steel/tubular structural alternatives for projects with weight restrictions. Typical floor build-ups are around 90 mm for the standard configuration and 110 mm for walk-in shower or embedded drainage configurations. These dimensions include 10 mm neoprene support pads and a minimum 5 mm leveling tolerance. Final dimensions are provided in approved-for-construction drawings before manufacturing begins.
What site preparation is required?
The site preparation for pod installation requires a level and structurally verified floor slab, with marked neoprene support locations. Recessed installations must be coordinated early in the design phase. Neoprene pads help accommodate minor tolerances and ensure proper alignment with surrounding floor finishes.
How are pods moved safely on site?
Pods are safely moved on site using certified lifting systems, including lifting bushings and defined anchor points. Depending on weight and configuration, handling may involve cranes or forklifts. The lifting strategy is agreed in advance to ensure safe installation.