Prefabricated bathroom pods - Prefabricated bathroom pods case study amory tower

Key Project Data

  • Location: Canary Wharf, London
  • Building: Amory Tower (The Madison) – 53 storeys
  • Sector: High-rise residential
  • Client: LBS Properties
  • Architect: Make Architects
  • Main Contractor: Balfour Beatty
  • Bathroom pods supplied: 487 prefabricated units (16 typologies)
  • Sterchele scope: Early-stage design coordination, off-site manufacture, sequenced delivery, and on-site technical integration support through installation and commissioning
Prefabricated bathroom pods - Prefabricated bathroom pods case study amory tower
Prefabricated bathroom pods - Prefabricated bathroom pods case study amory tower

The Challenge

Amory Tower is a 53-storey residential development delivered on a constrained urban site adjacent to Canary Wharf. The tower combines private and affordable apartments across multiple specification tiers within a slender structural footprint.

The scheme was originally designed for traditional in-situ bathroom construction. During delivery, a decision was made to incorporate prefabricated bathroom pods, requiring the adaptation of pod geometry to an existing layout rather than designing the building around a modular solution.

This required detailed coordination to align pod dimensions, service interfaces, and structural tolerances within a live high-rise design framework while maintaining programme continuity.

Our Solution

Sterchele was engaged from the design development stage to integrate bathroom pod technology into the established architectural and structural layout.

Our involvement included:

  • Detailed design coordination to adapt 16 pod typologies to existing apartment configurations
  • Interface alignment with structural grids, risers, drainage, ventilation, and containment strategies
  • Dimensional review to ensure compatibility with floor-to-floor tolerances and façade constraints
  • Factory-controlled manufacture with defined inspection and verification stages
  • Sequenced delivery aligned with the tower’s vertical construction programme
  • On-site technical presence during installation and commissioning to support coordinated service integration

The bathroom package was incorporated as a controlled modular system within a design not originally configured for pods.

Prefabricated bathroom pods - Prefabricated bathroom pods case study amory tower
Prefabricated bathroom pods - Prefabricated bathroom pods case study amory tower

Why Prefabricated Pods Were Effective

On a 53-storey tower with multiple apartment types, prefabrication provided operational control:

  • Consolidation of multi-trade bathroom works into a single manufactured unit
  • Repeatable installation methodology across varied typologies
  • Reduced labour intensity within vertical cores and apartment fit-out zones
  • Standardised quality verification prior to delivery
  • Installation sequencing aligned with floor-by-floor progression

The bathroom scope transitioned from dispersed trade activity to a coordinated modular installation process within a highly constrained urban site.

Outcome

The integration of prefabricated pods transformed bathroom delivery from variable, multi-trade on-site construction to a structured and repeatable modular process across 487 units.

This supported:

  • Programme predictability within a 53-storey build sequence
  • Reduced vertical trade congestion during peak installation phases
  • Consistent dimensional and finish standards across multiple specification tiers
  • Clear interface coordination between pod services and the building’s infrastructure

By integrating design adaptation, manufacture, delivery, and on-site technical support within a single structured scope, the bathroom package was delivered as a coordinated system within a complex high-rise environment.

Prefabricated bathroom pods - Prefabricated bathroom pods case study amory tower

Share

Learn more about bathroom pods in the UK

To learn more about the Group and our way of working, download our Company Profile by filling out the form with your details.

Other projects

CX San Pietro

288 Prefabricated Bathroom Pods Delivered for Large-Scale Student Accommodation

Greenwich Plot 19.05

562 Prefabricated Bathroom Pods Delivered Within a Hybrid Construction Framework

Amory Tower (The Madison)

487 Prefabricated Bathroom Pods Delivered for a 53-Storey Residential Tower